In order for achievements of Telecom Project Phase III faster than its durations, ETL has divided Telecom Project Phase III into 2 different phases: Telecom Project Phase IIIA & Telecom Project Phase IIIB.
1/. The Telecom Project Phase IIIA, started from May 2004 to May 2005.
Installed 2 Base Station Controllers in Vientiane Capital and Savannakhet Province.
Increased the capacity of Mobile Switching Center (MSC) from 100.000 subscribers to 200.000 subscribers.
Installed 91 Base Transmission Stations (BTS) for mobile phones.
Increased capacity of Billing System from 200.000 subscribers to
300.000 subscribers.
Completed to construct SDH transmission system by using Optical Fiber Cable speeding of 155 Mbps and 622 Mbps (STM1 & STM4).
Completed to expand Optical Fiber Cable with its full accessories have been installed in the lengths of 1.500 kilometers.